11-05-2009 02:32 PM
I need to move our current sync server to a new server. I have approx 80 remote users so I am hoping I do not have to recut databases. Can I just run a final sync on the old box and point the new sync server to the existing sync profile?
Many thanks! Doug
Solved! Go to Solution.
11-05-2009 03:41 PM
11-05-2009 03:46 PM
I fired up the new sync server, and pointed to my slx prod instance. It then asked me to register it with the database server, which i did. It then asked which sync server license to use (we have one in prod that I am looking to replace). Wondering if I can just select it and roll - the message says "It is important that you do not select a SyncServer that has already been installed on another computer."
Thanks
11-05-2009 03:51 PM
11-06-2009 11:33 AM
11-06-2009 11:39 AM
11-06-2009 11:42 AM
11-06-2009 11:56 AM